Start | Finish | Project Description |
---|---|---|
11/11/23 | IN PROGRESS | 2318: INT-EXT Roof Deck & Windows |
TBD | PENDING | 2327: INT Interior Painting |
07/23/24 | IN PROGRESS | 2329: INT-EXT Windows, Siding, Remove Wall |
TBD | PENDING | 2330: EXT Bulkhead and bulkhead stairs |
06/01/24 | IN PROGRESS | 2401: EXT Painting Porch Side |
TBD | PENDING | 2331: INT Bathroom Painting |
TBD | PENDING | 2332: EXT Repl. Siding, Seal to Wx |
TBD | 2333: EXT Painting, House Repair | |
TBD | 2334: EXT Corner Repl & Gutters | |
TBD | 2335: INT-EXT Misc. projects | |
TBD | 2336: EXT Shingle Siding & Gutter | |
TBD | 2337: Exterior wood shingles, siding/roof | |
TBD | 2339: Whole House Window Replacement | |
TBD | 2341: W/D Reloc., Pocket Door Inst., Painting | |
TBD | 2342: Wooden Gutter Sealing/Rework | |
12/11/23 | 2346: Shower replacement, etc. | |
TBD | 2402: EXT Paint Trim, Replace Rotten Trim | |
TBD | 2403: EXT Construct Shed Roof Over Tarp Barn | |
TBD | 2404: EXT Painting & Repair | |
TBD | 2405: EXT Decking & Sidewall Rot Repair | |
TBD | 2407: INT Install Tin Ceiling | |
TBD | 2408: EXT: Instal cricket over porch entry | |
TBD | 2409: INT: 3 phase room construction, deck, stairs | |
TBD | 2410: INT: Screen/window repair | |
TBD | 2411: EXT: Fascia replacement | |
TBD | 2412: EXT: Porch painting | |
TBD | 2413: EXT: Stairs down the bank to the beach | |
TBD | 2414: EXT: Cottage; paint windows | |
TBD | 2415: EXT: Painting, repair fascia, trim, siding | |
TBD | 2416: EXT: Fascia replacement |
October 2024 |
||||||
---|---|---|---|---|---|---|
Sun | Mon | Tue | Wed | Thu | Fri | Sat |
1
|
2
|
3
|
4
|
5
|
||
6
|
7
|
8
|
9
|
10
|
11
|
12
|
13
|
14
|
15
|
16
|
17
|
18
|
19
|
20
|
21
|
22
|
23
|
24
|
25
|
26
|
27
|
28
|
29
|
30
|
31
|